Pre-operations alignment with vessel

Operators representative shall ensure that the operations plan is communicated, per alignment mail, with the vessel as soon as practically possible.

  1. Estimated time and position of berthing.
  2. Starting time, number of shifts planned, breaks and expected intervals of no operations.
  3. Estimated Time of Completion and Departure (ETD).
  4. Suggested time and place for the ramp meeting.
  5. Number of working gangs.
  6. Working sequence - plan, including panel movements advise and / or cargo-shifting plan if relevant.
  7. Emergency contact procedures and any local safety and security information.
  8. Dangerous Goods list.
  9. If the Master have special request this must be communicated as soon as possible, in order to have enough time for organizing if necessary (example: extra labor might be needed).The Master shall revert on the pre-operational alignment message without delay confirming all understood or ask for clarification/additional information.
  10. Lashing management to be aligned between stevedores and vessel: placing rubber mats on behalf of vessel and on behalf of cargo (anti slip in stow or on ramps)) / moving of lashing / equipment boxes.